675 Mw Combined Cycle Perlis independent power plant.
LOCATION : Malaysia
SERVICE : Construction Management
VALUE : Confidential
SIZE : 675 MW IPP
CLIENT : Tenaga National Berhad
TYPE : Energy
OVERVIEW
The Project is based on three Alstom GT13E2 gas turbines exhausting through dual pressure heat recovery system generators, which provide steam to a typical standard pressure steam turbine.
With a net site output of 675 MW with power augmentation in the form of water injection. The projects also involved the engineering, procurement and supply of a 132 kV and 275 kV switchyard, which was handed over to the Tenaga National Berhad (T.N.B. Malaysia’s Power Authority) under the terms of the power purchase agreement upon completion.
Since 1996, Kingston was involved in the delivery of a 675 MW Combined Cycle Perlis Independent Power plant/I.P.P., alongside a Consortium composed by Peremba / Alstom Power.